92 

 

 

Internal energy sources evaluated (e.g., biogas, hydropower, heat in wastewater), and/or 
renewable energy sources evaluated on an ongoing basis (e.g., solar, wind, co-digestion)  

 

Solar panels, wind turbines, heat recovery, in conduit hydro, and/or hydroelectric power 
generation systems installed  

Currently working to implement anaerobic digestion and CHP by 2019. 

PPA for 2.5MW Solar Energy Project on adjacent Superfund site.  

Completed replacement of Multistage Blowers with High Efficiency single stage blower resulting in a two 
million kWh/y reduction. 

Completed replacement of all outdoor lighting with LED. 

Purchased Green Energy Blocks from supplier. 

Performance Measures & Results 

Your Performance Measure(s) 

Your Results (quantitative or qualitative) 

Future – Percent Gris,  Solar 
Power, Biogas and Green Energy 
Blocks 

Future 

Cost Savings by individual project. 

South Plant Real-time Nitrogen Control -675,000 kWh/y 
E. coli of UV – 725,000 kWh/y 
 
North Blower Replacement – 2,000,000 kWh/y 
Lighting Projects 
Outdoor Lighting
 – At the WRRF we replaced a total of 270 outdoor Metal 
Halide and High Pressure Sodium lighting fixtures with LED fixtures of the same 
style. The LED fixture cost was $63,981 and we will be receiving $10,622 from a 
Consumers Energy rebate to help offset this cost. We had a $10,550 
installation cost and an estimated $4,400 annual maintenance savings due to 
the expected 22 year life of the lamps. With an energy savings of $10,468 per 
year, calculated at 9 cents per kW hour at 12 hours on time per day, our 
expected payback in this investment will be 4.3 years. 
 
Tunnel Lighting – At the WRRF we replaced a total of 137 indoor compact 
fluorescent lamps, located in the underground tunnel system, with LED lamps 
of the same style. The LED lamp cost was $2,048 and was not eligible for a 
Consumers Energy rebate. We had a $1,674  installation cost, which will be 
more than offset by the annual maintenance savings, estimated at 
$1,005/year, due to the expected 3 year life of the lamps. With an energy 
savings of $1,782 per year, calculated at 9 cents per kW hour at 24 hours on 
time per day, our expected payback in this investment will be 1.3 years. 
 
Sewer Maintenance Garage Lighting – At the Sewer Maintenance Facility 
garage area we replaced a total of 27 indoor 400 Watt High Pressure Sodium 
lighting fixtures with 128 Watt Fluorescent fixtures. The fixture cost was 
$2,084 and we will be receiving $1,563 from a Consumers Energy Rebate to 
help offset this cost.  We had an actual $3,331 installation cost. With an energy 
savings of $2,465 per year, calculated at 9 cents per kW hour and 60 hours on 
time per week, our expected payback in this investment will be 1.6 years.

 

D.O.E EnPI 

Electricity (MMBTU) -215,964